Progress Claim Report

The information displayed in this report is specific to Progress Claim(s) and displays the most recent project data based from your search results.

  1. Standard Report - Available to all users.
Column Header Description
Contract Contract Type
Number Progress Claim Number
Status Progress Claim Status
Net Change by CO Calculated as the sum of Change Order(s) linked to the Progress Claim and Change Order(s) linked to previously issued Progress Claim(s)
Revised Contract Amount Calculated as the sum of the Original Contract Value and Net Change by CO
Total Completed to Date Total amount billed to date
Retention Released Amount released from the Total Retained Amount
Claim Amount Total Value of Work for the period
Claim Amount with Tax Total Amount of the Certificate (including tax)

See Progress Claim Standard Report to view the standard Progress Claim Report template.