Acknowledge a Change Directive

When a Change Directive has been issued on a project, and you are the General Contractor Project Manager, you will receive an action item on your Home page requesting that the Change Directive be acknowledged. You can also access the document on the Change Directive Search page.

To acknowledge a Change Directive:

  1. Click on the Project that contains the Change Directive in you Action Itemslist.

The Action Items list expands.

Tip: Documents requiring your review will be labeled "Acknowledgment Required" after the document title.

  1. Click the Action Item.

The Change Directive Acknowledgment page displays.

Note: Any linked documents within the Change Directive will display in the Linked Documents section.

  1. Review the Change Directive, and any attachments or comments entered by the Contract Administrator or Owner's Project Manager.
  1. Complete any additional fields:
  2. To action the Change Directive, select one of action buttons from the top toolbar:
  1. the Change Directive. For more information, see Acknowledge a Document.
Who's next?
Contract Administrator to review and close the Change Directive. For more information, see Close a Change Directive
What's next?
A confirmation page affirming all required information is completed and the document has successfully transitioned to the identified status.
  1. If there is missing or incorrect information:
  • Enter a comment addressing the reason for returning the Change Directive.
  • Click . For more information, see Return a Document.
Who's next?
Contract Administrator to review the Change Directive. For more information, see Issue a Change Directive
What's next?
A confirmation page affirming all required information is completed and the document has successfully transitioned to the identified status.