Approve a Change Directive

If a Change Directive has been issued on a project, and you are the Owner's Project Manager, you will receive an Action Item on your Home page to approve the Change Directive. You can also access the document on the Change Directive Search page.

To approve a Change Directive:

  1. Click on the Project that contains the Change Directive in your Action Items list.

The Action Items list expands.

Tip: Documents requiring your review will be labeled "Approval Required" after the document title.

  1. Click the Action Item.

The Change Directive Approve page displays.

  1. Review the Change Directive, and any attachments or comments entered by the Contract Administrator.
  2. Complete any additional fields:
  1. To action the Change Directive, select one of action buttons from the top toolbar:
    1. If there is missing or incorrect information:
    • Enter a comment addressing the reason for returning the Change Directive.
    • Click . For more information, see Return a Document.
Who's next?
Contract Administrator to review the Change Directive. For more information, see Issue a Change Directive
What's next?
A confirmation page affirming all required information is completed and the document has successfully transitioned to the identified status.
    1. the Change Directive. For more information, see Approve a Document.
  • Who's next?
    General Contractor Project Manager to review and acknowledge the Change Directive. For more information, see Acknowledge a Change Directive
    What's next?
    A confirmation page affirming all required information is completed and the document has successfully transitioned to the identified status.